Big concrete pour at the site today!


The mat slab is being poured, 400 yards of concrete (about 40 trucks). The mat slab is the large area with lots of rebar in the photo. This will be under the auditorium.

Trucks will load into the pump truck on Fell street and pump from there onto the site.

The action will be very visible from the street (linden alley will be a great vantage point).